Industrial Engineering And Production Management - Study Mode
[#106] A big advantage of PERT over Gantt charts is that in the former case
Correct Answer
(D) Interrelationship among activities is clearly shown
Explanation
Solution: A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shown
[#107] Which of the following conditions are necessary for applying linear programming?
Correct Answer
(D) All of the above
Explanation
Solution: following conditions are necessary for applying linear programming is listed below: - These must be a well defined objective function. - The decision variables should be interrelated and nonnegative. - The resources must be in limited supply.
[#108] The term 'value' in value engineering refers to
Correct Answer
(C) Utility of the product
Explanation
Solution: The term 'value' in value engineering refers to Utility of the product
[#109] For a product layout the material handling equipment must
Correct Answer
(D) Be designed as special purpose for a particular application
Explanation
Solution: For a product layout the material handling equipment must Be designed as special purpose for a particular application
[#110] Work sampling is applied for
Correct Answer
(D) All of the above
Explanation
Solution: Work sampling is applied for - Estimation of the percentage utilization of machine tools - Estimating the percentage of the time consumed by various job activities - Finding out time standards, specially where the job is not repetitive and where time study by stop watch method