[#96] A diagram showing the path followed by men and materials while performing a task is known as
Correct Answer
(D) Flow diagram
Explanation
Solution: A diagram showing the path followed by men and materials while performing a task is known as Flow diagram
[#97] The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode
Correct Answer
(A) Early finish
Explanation
Solution: The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early finish
[#98] Standard time is equal to
Correct Answer
(B) (Normal time) + (allowances)
Explanation
Solution: Standard time is equal to (Normal time) + (allowances) the standard time is the time required by an average skilled operator, working at a normal pace, to perform a specified task using a prescribed method.
[#99] Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?
Correct Answer
(C) Halsey premium plan
Explanation
Solution: Halsey premium plan method, standard time for doing each job or operation is fixed and the worker is given wages for the actual time he takes to complete the job or operation at the agreed rate per hour plus a bonus equal to (usually) one-half of the wages of the time saved
[#100] Routing is essential in the following type of industry
Correct Answer
(A) Assembly industry
Explanation
Solution: Routing is the hub around which all of IP connectivity revolves. At the simplest level, routing establishes basic internetwork communications, implements an addressing structure that uniquely identifies each device, and organizes individual devices into a hierarchical network structure