[#96] A river training work is generally required when the river is
Correct Answer
(A) Meandering
(G) meandering type
[#97] In a chute spillway, the flow is usually
Correct Answer
(D) super critical
[#98] Groynes are generally built
Correct Answer
(B) Inclined up stream up to 30°
[#99] The rainfall on five successive days were measured as 100 mm, 80 mm, 60 mm, 40 mm and 20 mm respectively. If the infiltration index or the storm loss rate for the catchment area is earlier estimated as 50 mm/day, the total surface run off will be
Correct Answer
(C) 90 mm
[#100] When a canal and a drainage approach each other at the same level, the structure so provided, is
Correct Answer
(C) A level crossing