Construction Planning And Management - Study Mode
[#86] A critical ratio scheduling
Correct Answer
(D) None of these
[#87] A golden rule for the procurement of construction stones, suggests
Correct Answer
(B) 67% at the site and 33% under procurement
[#88] If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Correct Answer
(C) $$frac{{{ ext{a}} + 4{ ext{m}} + { ext{b}}}}{6}$$
[#89] For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
Correct Answer
(A) Moist loam
[#90] The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
Correct Answer
(C) Rs. 6,400