[#76] An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
Correct Answer
(A) Rs. 31050
[#77] Works costing less than Rs. 20,000 are treated as
Correct Answer
(D) Petty works
Explanation
Solution: In Civil Engineering, works costing less than Rs. 20,000 are typically categorized as Petty works . These are small-scale projects of minor significance that require minimal resources and planning. Therefore, the correct option is D: Petty works .
[#78] If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
Correct Answer
(D) 16 days
[#79] Time and progress chart of a construction, is also known as
Correct Answer
(D) All the above
[#80] The difference between the time avail-to do a job and the time required to do the job, is known as
Correct Answer
(B) Float