[#321] What is the major advantage of using Incremental Model?
Correct Answer

(D) Easier to test and debug & It is used when there is a need to get a product to the market early

[#322] CCB stands for
Correct Answer

(A) Change Control Board

[#323] Which of the following model has a major disadvantage in terms of the coding phase of a software life cycle model ?
Correct Answer

(D) 4GT Model

[#324] Which of the following process is concerned with analyzing the costs and benefits of proposed changes?
Correct Answer

(A) Change management

[#325] In reverse engineering, what refers to the level of detail that is provided at an abstraction level?
Correct Answer

(B) completeness