[#96] Number offish bolts per fish plate is
Correct Answer

(B) 4

[#97] The following tests are conducted for rails: i) falling weight test ii) tensile test iii) hammer test The compulsory tests are
Correct Answer

(B) (i) and (ii)

[#98] Stretcher bar is provided
Correct Answer

(B) To maintain the two tongue rails at the exact distance

[#99] Dog spikes are used for fixing rail to the
Correct Answer

(A) wooden sleepers

[#100] Consider the following surveys i) Reconnaissance survey ii) Preliminary survey iii) Traffic survey iv) Location survey The correct sequence in which these surveys are conducted before the alignment of a track is finalised is
Correct Answer

(D) iii, i, ii, iv