Opencast Mining - Study Mode

[#286] Bench height - 12 m, burden - 4 m, spacing - 5 m, explosive per hole - 120 kg, density of rock - 2600 kg/m 2 is the power factor in tonne/kg is . . . . . . . .
Correct Answer

(C) 5.2

[#287] The ratio at which the cost of open cast mining equals that of under ground mining is
Correct Answer

(A) Break even stripping ratio

[#288] In India coal seams with inclination as steep as . . . . . . . . have been worked by mechanical open cast.
Correct Answer

(B) 1 in 3

[#289] The maximum size of the boulder that can loaded by shovel is times the bucket capacity.
Correct Answer

(C) 0.8

[#290] The mining which is not completely effected by weather.
Correct Answer

(D) Underground mining