[#111] If the depth of the shaft exceeds 1000 m but not 1500 m, no winding rope shall be used or continued to use, if its factor of safety is becomes less than . . . . . . . . in metal mines.
Correct Answer

(C) 6

[#112] In cut and fill stoping is done by . . . . . . . .
Correct Answer

(D) All the above

[#113] The method of stoping suitable to extract thick ore body strong ore, stable handling and footwall steeply dipping ore is . . . . . . . .
Correct Answer

(B) Sub level

[#114] The friable rock in cut and fill method is supported by . . . . . . . .
Correct Answer

(B) Cable bolting

[#115] The number of persons required for collection of samples in u/g.
Correct Answer