[#191] A systematic job improvement sequence will consist of
Correct Answer
(D) All of these
Explanation
Solution: A systematic job improvement sequence will consist of Motion study Time study Job enrichment
[#192] The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
Correct Answer
(A) Inflated system
Explanation
Solution: The wastage of material in the store is taken into account by the inflated system method in the evaluation of the material issued from the store.
[#193] Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Correct Answer
(B) One-half
Explanation
Solution: Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is One-half the standard time.
[#194] Critical Path Net Work helps an engineer
Correct Answer
(D) All of the above
Explanation
Solution: Critical Path Net Work helps an engineer - To concentrate his attention on critical activities - To divert the resources from noncritical advanced activities to critical activities - To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
[#195] Queueing theory is used for
Correct Answer
(D) All of the above
Explanation
Solution: Queueing theory is used for - Inventory problems - Traffic congestion studies - Job-shop scheduling