Industrial Engineering And Production Management - Study Mode
[#131] The difference between the time available to do the job and the time required to do the job, is known as
Correct Answer
(B) Float
Explanation
Solution: The difference between the time available to do the job and the time required to do the job is known as Float
[#132] In A-B-C analysis, which class of items are generally large in number?
Correct Answer
(C) C
Explanation
Solution: ABC analysis is a type of inventory categorization method in which inventory is divided into three categories, A, B and C in descending value. Inventory management and optimization in general is critical for business to help keep their costs under control. In A-B-C analysis, C class of items are generally large in number.
[#133] Which one of the following chart gives simultaneously information about the progress of work and machine loading?
Correct Answer
(C) Man-machine chart
Explanation
Solution: A man-machine chart graphically represents the relationship between the manual work performed by one or more operators and one or more machines involved in a manufacturing process.
[#134] The important file in making a PERT is
Correct Answer
(D) All of the above
Explanation
Solution: The important file in making a PERT is 1. An event can't be accomplished until activities leading to it are completed 2. No activity from any event can be started from preceding event till it is completed 3. Length of arrow has nothing to do with time
[#135] Which of the following layouts is suited for mass production?
Correct Answer
(B) Product layout
Explanation
Solution: Work is done in small amounts at each of the work stations on the line. To use the product layout, the total work to be performed must be dividable into small tasks that can be assigned to each of the work stations. Because the work stations each do small amounts of work, the stations utilize specific techniques and equipment tailored to the individual job they are assigned. This can lead to a higher rate of production.