[#616] Match the following List I (Dam) List II (River) a. Nathpa Jhakri 1. Beas b. Girinagar 2. Ravi c. Chamera 3. Sutlej d. Pandoh 4. Giri
Correct Answer
(C) a-3, b-4, c-2, d-1
[#617] Which of the following is not the aim and objective of the Himachal Pradesh Solar Power Policy, 2016? 1. Promote generation of electricity from solar energy for sustainable development. 2. Empower people in the remote and rural areas with 24 × 7 powers by way of decentralised solar power supply. 3. Create awareness about potentials of renewable energy. 4. Strengthen and sustain the policy of 100% clean electricity consumption.
Correct Answer
(D) None of the above
[#618] Nathpa Jhakhri Hydro Electricity Power Project has the capacity of ............... MW.
Correct Answer
(B) 1500 MW
[#619] Which of the following states sharess the hydro power generated through Bhakra Nangal Dam? 1. Punjab 2. Rajasthan 3. Uttarakhand 4. Gujarat Select the correct answer
Correct Answer
(B) 1, 2 and 4
[#620] How many members are included in HPSEBL including its Chairman.
Correct Answer
(A) 7 members