Financial Management - Study Mode
[#426] An expected final stock price is Rs 70 and an expected capital gain is Rs 25 then an original investment would be
Correct Answer
(A) Rs 45.00
Explanation
Solution: Original investment = Expected final stock price - Expected capital gain = Rs. 70 - Rs. 25 = Rs. 45.00
[#427] Business risk can be measured by:
Correct Answer
(B) Operating leverage
[#428] Between two capital plans, if expected EBIT is more than indifference level of EBIT, then:
Correct Answer
(C) One is better than other
[#429] Ageing schedule incorporates the relationship between:
Correct Answer
(B) Debtors and Days Outstanding
[#430] EOQ determines the order size when:
Correct Answer
(C) Total Inventory Cost is minimum