Construction Planning And Management - Study Mode
[#1] Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is
Correct Answer
(C) 1, 2, 3, 4, 5
[#2] The salient feature of functional organization is
Correct Answer
(D) All the above
[#3] The time corresponding to minimum total project cost is
Correct Answer
(D) Between normal time and crash time
[#4] The process of incorporating changes and rescheduling or replanning is called
Correct Answer
(C) Updating
[#5] If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
Correct Answer
(D) All the above